The Lagoons Phase One
None of The Lagoons Phase One’s 2 dated live projects is past the completion date it registered itself: 0%, against 13% across the 28 Dubai developers with ten or more registered projects. Its most-traded tower, The Grand, registered 85 sales in the last 12 months at a median AED 3.26M (AED 2,754/sqft).
Live projects past their registered date
0%0 of 2
28 developers with ten or more projects: 13%
- Registered projects
- 21
- Completed
- 19
- Live, no registered date
- 0
Does The Lagoons Phase One deliver on time?No dated live project is past its own registered date; its most-traded tower sells at a typical AED 3.26M (AED 2,754/sqft)
- Are live projects on time?0 of 2 dated live projects are past the date The Lagoons Phase One registered0%Context
- How does it rank?Not ranked: the ranking needs 5 live projects, so one slipped project cannot swing the shareNo record
- How late, typically?Median 7 months early over 5 completions with a date distinct from the plan; 14 more were stamped with it−7 moContext
- Do its towers trade?The Grand trades at AED 2,754/sqft on 85 sales, off-plan and ready, in 12 months; 46 of its towers have a sale recordAED 3.26MContext
Ranked on the share of live projects past their own registered date · fewest first · register Jul 2026
Live projects, most advanced first2 live projects, none past their registered date
Built % and dates from the DLD register, Jul 2026 · months past date at that register date · a live project past its date is overdue, not late: it has not been delivered, and this site does not forecast when it will be
Delivered projects, most recent first19 completed; the median measurable completion came 7 months early
Show the 19 delivered projectsHide the delivered projects
Slippage is months from the registered date to the recorded one; negative is early. The register dates 14 of these 19 completions to the registered day exactly — it writes the completion date onto the planned one — so those are marked “stamped” and left out of the median rather than counted as on time.
The Lagoons Phase One towers on the marketIts towers trade between AED 1,495 and 3,580 per sqft
Registered sales, ready and off-plan, in the 12 months to · attribution follows the project each tower was registered under · the 8 most traded of 46
Every project the Dubai Land Department registers to The Lagoons Phase One, matched by the developer licence number on each registration — a medium-confidence identity.
Common questions
- Are The Lagoons Phase One's off-plan projects on time?
- 0 of The Lagoons Phase One's 2 dated live projects are past the completion date the developer registered itself (0%), against 13% across the 28 Dubai developers with ten or more registered projects. Being past the date is a fact about today, not a forecast of when a project will finish. Dubai Land Department project register to 2026-07-06.
- How does The Lagoons Phase One rank against other Dubai developers on delivery?
- The Lagoons Phase One is not ranked: it has 2 live projects, and the ranking needs 5 so that one slipped project cannot swing the share. Dubai Land Department project register to 2026-07-06.
- How late are The Lagoons Phase One's completed projects, typically?
- The median measurable completion finished 7 months before its registered date, over 5 completions; 100% of those landed on or before it. 14 more completions were dated to the registered day exactly, where no slippage is observable, and are excluded. Dubai Land Department project register to 2026-07-06.
- How many projects has The Lagoons Phase One registered in Dubai?
- 21 registered projects: 2 live, 19 completed. Projects are matched to The Lagoons Phase One by the developer licence number on each registration. Dubai Land Department project register to 2026-07-06.
- What do The Lagoons Phase One's towers sell for?
- Its most-traded tower, The Grand, sold at a median AED 2,754/sqft across 85 registered sales, off-plan and ready, in the last 12 months. These are prices paid, not asking prices.
For agents
Send The Lagoons Phase One’s delivery record to a client
The Lagoons Phase One, delivery record
- Record type
- Developer-level off-plan register record
- Data date
- Evidence base
- 21 registered projects, 2 live of which 0 past their registered date, 5 completions with a measurable slippage of 19 completed; DLD project register as of 2026-07-06; identity medium-confidence over 1 licensed company
- Sources
- Dubai Land Department project register
- Canonical record
- /developers/the-lagoons-phase-one
Cite as: Dubai Wealth Index. “The Lagoons Phase One, delivery record.” Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/developers/the-lagoons-phase-one