Terhab Hotel & Towers at Jumeirah Village Triangle
Recorded complete in November 2021.
Started Feb 2016Completed Nov 2021
DLD project register, Jul 2026
- Titles issued
- 764 of 764
- Escrow
- بنك دبي الاسلامي (شركة مساهمة عامة)
Saves the tower’s record to your account.
Is Terhab Hotel & Towers at Jumeirah Village Triangle a safe off-plan buy?Recorded complete in November 2021; no record of the builder
- Is it on schedule?Recorded complete in November 2021, on its registered date to the day: the register often stamps one onto the other · DLD project register, Jul 2026100%Context
- Is my money protected?The register named the escrow agent: بنك دبي الاسلامي (شركة مساهمة عامة)EscrowContext
- Is the price fair?No off-plan sale registered in 12 months to price it onNo record
- Is it selling?No off-plan sale registered in 12 months; the last in December 20240Context
- Who is building it?The register names the master developer, Jumeirah Village; the builder is not recordedNo record
A registered date is not a delivery forecast · 79% of recorded completions carry their planned date to the day · DLD register, July 2026
What is being built764 units, mostly studios; all titled
DLD unit register · balconies a median 17% of unit area
Every unit, floor by floor →Sizes run from the 10th to the 90th percentile of registered floor area, so one mislabelled unit cannot set the range. A title is issued at handover: a live project shows few or none however many units have sold, and an untitled unit is not necessarily for sale.
Every unit, as registered
764 units in DLD’s register for Terhab Hotel & Towers at Jumeirah Village Triangle, floor by floor.
Show 400 of 764 unitsHide the units
A title is issued at handover. “Not yet” means no title, which a reserved unit and an unsold one share; the register does not say which is for sale.
How other Jumeirah Village Triangle projects are tracking2 of the 3 nearest-to-finished are past their registered dates
“Past date”: the registered date has already passed · 3 of 22 live Jumeirah Village Triangle projects past theirs · DLD register and inspections, October 2026
All 60 Jumeirah Village Triangle projects →As registered with the Land DepartmentWhere Terhab Hotel & Towers at Jumeirah Village Triangle is, and who is on its register row
- Escrow agent
- بنك دبي الاسلامي (شركة مساهمة عامة)
- Master developer
- Jumeirah Village
- Registered start
- February 2016
- Configuration
- HOTEL & HOTEL APARTMENT (B+G+4P+3 FACILITIES + TOWER 16 FLOORS &TOWER 45 FLOORS) +roof+ up roof. with external and internal finishes.
Construction progress is the percentage DLD recorded in its project register as of July 2026, the latest DLD record for this project; the register lags DLD’s inspections by months, so it is dated separately. The developer is the company licensed to build it, by the register’s own licence number; the master developer owns the land under it and is often another company entirely. Off-plan price is the median of registered off-plan sales across this project’s published buildings, 12 months to .
Published buildings in Terhab Hotel & Towers at Jumeirah Village Triangle
Towers inside this project that have enough registered resales for their own record.
Ask about Terhab Hotel & Towers at Jumeirah Village Triangle
Looking to buy or rent here? Tell us what you need: unit type, budget, timing.
We reply by phone, WhatsApp or email, and put you in touch with a licensed agent.
Common questions
- When will Terhab Hotel & Towers at Jumeirah Village Triangle be completed?
- The register records Terhab Hotel & Towers at Jumeirah Village Triangle complete in November 2021. Dubai Land Department project register as of July 2026.
- Is Terhab Hotel & Towers at Jumeirah Village Triangle in escrow?
- Yes: the Land Department register names بنك دبي الاسلامي (شركة مساهمة عامة) as the project’s escrow agent, the bank that holds buyers’ payments for the developer. Dubai Land Department project register as of July 2026.
- Who is the developer of Terhab Hotel & Towers at Jumeirah Village Triangle?
- The register names the master developer, Jumeirah Village, which owns the land; the company building the project is not recorded. Dubai Land Department project register as of July 2026.
- How many units does Terhab Hotel & Towers at Jumeirah Village Triangle have?
- 764 registered units, of which 764 have a title issued. A title is issued at handover, so a live project shows few or none however many units have sold. Dubai Land Department project register as of July 2026.
For agents
Send Terhab Hotel & Towers at Jumeirah Village Triangle to a client as a branded report
Off-plan record for Terhab Hotel & Towers at Jumeirah Village Triangle
- Record type
- Project-level off-plan register record
- Data date
- Evidence base
- 764 registered units; DLD project register as of 2026-07-06
- Sources
- Dubai Land Department project register, construction inspections and title register; sale transactions
Cite as: Dubai Wealth Index. “Terhab Hotel & Towers at Jumeirah Village Triangle, off-plan.” Jumeirah Village Triangle, Dubai. Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/off-plan/apartments/dubai/jumeirah-village-triangle/terhab-hotel-and-towers-at-jumeirah-village-triangle