District 11 upcoming supply
Every pending apartment project in District 11, by when it is due, set against the homes let there today. Prices and yields in District 11 · Off-plan launches
- Data to
- Pending projects
- 10
- Pending units
- 696
District 11: 696 apartments planned for 2026–2028, 2486% of the homes let there today
Counted against today, 2026-10-18. Register to 2026-07-06; leases to 2026-10-12.
- Planned 2026–28
- 696
- 696 pending in all
- Homes let today
- 28
- Ejari tenancies in force
- Planned ÷ homes let
- 2486%
- Too few leases for a ratio
- Due in 12 months
- 343
- 0 already past their date
When it is due
Every pending apartment, by its registered completion quarter.
Handover calendar
Apartment units, by planned completion quarter
- Q4 ’26: 138138
- Q1 ’27: 7575
- Q2 ’27: 130130
- Q3 ’27: 00
- Q4 ’27: 9191
- Q1 ’28: 182182
- Q2 ’28: 8080
- Q3 ’28: 00
- Q4 ’28: 00
Which homes, against which lets
Planned for 2026–2028 by bedroom type, against the homes of that type let today.
Planned apartments
Units due 2026–2028, by bedroom type
- 1 bed381
- 2 bed306
- 3 bed9
Planned as a share of homes let today
Planned units ÷ registered tenancies in force
How the pressure has moved
Each point is one monthly report: the same measure, recomputed for that month's end.
Planned supply as a share of homes let
Planned units for the next three calendar years ÷ tenancies in force, %
Project calendar
10 pending projects, 696 units. Progress is the register's reported share built.
2026 Q4138 units · 2 projects
- High Best Tower2026-11-018491%
- The Cube Quarter Residences2026-12-315457%
2027 Q175 units · 1 project
- Woodland Terraces2027-03-30750%
2027 Q2130 units · 3 projects
- The Willows Residences2027-06-30540%
- Rome 2 by SD2027-06-30402%
- The Collection by NASER2027-06-30360%
2027 Q491 units · 2 projects
- Derby Heights2027-10-315110%
- Rome by SD2027-12-31403%
2028 Q1182 units · 1 project
- Gate Eleven Residences2028-03-311820%
2028 Q280 units · 1 project
- Rome 3 by SD2028-06-30800%
Method and limits
Planned supply is every apartment unit in a project the Land Department register lists as neither complete nor cancelled, placed by its registered completion date and counted against today. Homes let today are the registered Ejari tenancies in force on the data date. A planned date is the developer's, not a delivery forecast; completions slip, and some homes are owner-occupied or let short-term.
Why tenancies and not the register: the unit register only reaches back to recently registered projects, so it misses most of the homes standing today. Ejari records every registered lease with its start and end. Full methodology
District 11 upcoming apartment supply
- Record type
- Planned supply against tenancies
- Data date
- Evidence base
- 696 pending apartment units in 10 projects; 28 tenancies in force
- Sources
- Dubai Land Department project and unit registers; Ejari tenancies
- Canonical record
- /supply/apartments/dubai/mbr-city-district-11
Cite as: Dubai Wealth Index. “District 11 upcoming apartment supply.” District 11, Dubai. Data to 2026-10-12. https://dubaiwealthindex.com/supply/apartments/dubai/mbr-city-district-11