1,286 projects not recorded complete · 1,380 recorded complete · 26 recorded cancelled.

Search and filter projects →

Check projects that have not yet been recorded complete, including those with no ready-sale evidence. Construction progress and dates come from the Dubai Land Department register; a planned date is not a forecast and 100% progress alone does not establish handover.

Of the 1,286 projects not recorded complete, 1,286 have a reported progress percentage and 1,138 have a planned completion date. “Not supplied” means the register did not provide that field. Records dated 2026-11-01.

This directory includes every published named apartment or villa project with at least ten registered units. Smaller and unnamed register entries are outside this publication cohort. Open a project for its evidence, progress history where available and source dates.

Looking for one project, or for “not complete, 50–90% built, planned date passed”? Search and filter the register.

Remraam

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
RemraamApartment project · 11,422 registered unitsRecorded complete1002013-09-162011-12-312026-11-01
Remraam - Al RamthApartment project · 806 registered unitsRecorded complete1002021-12-162021-12-162026-11-01

Reportage Hills

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
Reportage HillsVilla project · 902 registered unitsNot recorded complete0.392028-06-30Not recorded2026-11-01

Reportage Village

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
Reportage Village 1Villa project · 1,752 registered unitsNot recorded complete25.042027-12-31Not recorded2026-11-01

Rukan

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
RukanApartment project · 621 registered unitsRecorded complete1002023-01-182023-01-182026-11-01
Rukan2Villa project · 49 registered unitsRecorded complete1002022-08-302022-08-302026-11-01
Rukan 3Villa project · 1,089 registered unitsRecorded complete1002022-12-312026-07-162026-11-01
Rukan ResidenceApartment project · 144 registered unitsRecorded complete1002024-02-282024-02-282026-11-01

Sobha Hartland

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
Berkeley PlaceApartment project · 127 registered unitsRecorded complete1002024-12-312024-12-312026-11-01
Gemini SplendorApartment project · 134 registered unitsRecorded complete1002018-10-072018-10-072026-11-01
Kensington WatersApartment project · 277 registered unitsRecorded complete1002024-06-302024-06-302026-11-01
Sobha Creek Vista HeightsApartment project · 1,342 registered unitsNot recorded complete91.53Not suppliedNot recorded2026-11-01
Sobha Creek VistasApartment project · 780 registered unitsRecorded complete1002022-01-172021-12-312026-11-01
Sobha Creek Vistas GrandeApartment project · 397 registered unitsRecorded complete1002025-07-312025-07-312026-11-01
Sobha Creek vistas ReserveApartment project · 780 registered unitsRecorded complete1002023-08-302023-08-302026-11-01
Sobha Hartland - Crest GrandeApartment project · 965 registered unitsRecorded complete1002026-06-302026-04-152026-11-01
Sobha Hartland Greens- Phase IApartment project · 161 registered unitsRecorded complete1002018-09-182018-09-302026-11-01
Sobha Hartland Greens Phase IIApartment project · 341 registered unitsRecorded complete1002020-01-062020-01-062026-11-01
Sobha Hartland Greens - Phase IIIApartment project · 495 registered unitsRecorded complete1002021-01-112021-01-112026-11-01
Sobha Hartland One Park AvenueApartment project · 403 registered unitsRecorded complete1002023-04-152022-09-162026-11-01
Sobha Hartland - The CrestApartment project · 1,496 registered unitsRecorded complete1002025-12-312025-12-312026-11-01
Sobha Hartland WavesApartment project · 592 registered unitsRecorded complete1002024-03-312024-03-312026-11-01
Sobha Hartland Waves GrandeApartment project · 432 registered unitsRecorded complete1002023-10-312024-10-312026-11-01
Sobha Hartland Waves OpulenceApartment project · 355 registered unitsRecorded complete1002026-09-302026-08-062026-11-01
The HighburyApartment project · 342 registered unitsNot recorded complete80.03Not suppliedNot recorded2026-11-01
The TerracesApartment project · 245 registered unitsRecorded complete1002022-02-152022-02-152026-11-01
Wilton Park ResidencesApartment project · 320 registered unitsRecorded complete1002023-06-252023-06-252026-11-01
Wilton TerracesApartment project · 283 registered unitsRecorded complete1002021-12-312022-01-052026-11-01

Sobha Sanctuary

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
The Brooks at Sobha SanctuaryVilla project · 184 registered unitsNot recorded complete02030-08-31Not recorded2026-11-01
The Greens at Sobha SanctuaryVilla project · 371 registered unitsNot recorded complete02030-08-31Not recorded2026-11-01
The WoodsApartment project · 1,264 registered unitsNot recorded complete02030-12-30Not recorded2026-11-01

Sufouh Gardens

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
113 ResidencesApartment project · 113 registered unitsNot recorded complete02029-02-28Not recorded2026-11-01
Acacia AvenuesVilla project · 57 registered unitsRecorded complete1002013-12-312015-01-252026-11-01
Al BahiaApartment project · 48 registered unitsRecorded cancelled1002014-05-272014-05-272026-11-01
Biltmore SufouhApartment project · 477 registered unitsNot recorded complete87.622026-01-29Not recorded2026-11-01
HilianaApartment project · 175 registered unitsRecorded complete1002014-09-112014-09-112026-11-01
J5Apartment project · 48 registered unitsRecorded complete1002015-08-272015-08-272026-11-01
J8Apartment project · 92 registered unitsRecorded complete1002016-09-012016-09-012026-11-01
Varazze TowerApartment project · 242 registered unitsRecorded cancelled91.532024-02-172021-06-062026-11-01

The Greens

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
Golf HeightsApartment project · 277 registered unitsRecorded complete1002026-12-312026-06-182026-11-01
MoselaApartment project · 351 registered unitsRecorded complete1002010-09-012010-09-012026-11-01
PanoramaApartment project · 224 registered unitsRecorded complete1002015-01-042015-01-042026-11-01
TanaroApartment project · 249 registered unitsRecorded complete1002010-09-012010-09-012026-11-01
The HillsApartment project · 426 registered unitsRecorded complete1002019-04-152019-04-152026-11-01
The OnyxApartment project · 169 registered unitsRecorded complete1002016-03-312015-12-312026-11-01

The Lakes

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
The Lakes - Deema 1Villa project · 65 registered unitsRecorded complete1002003-01-012003-01-012026-11-01
The Lakes Deema 2Villa project · 50 registered unitsRecorded complete1002003-01-012003-01-012026-11-01
The Lakes Deema 3Villa project · 53 registered unitsRecorded complete1002003-01-012003-01-012026-11-01
The Lakes Deema 4Villa project · 56 registered unitsRecorded complete1002003-01-012003-01-012026-11-01
The Lakes GhadeerVilla project · 138 registered unitsRecorded complete1002007-01-012007-01-012026-11-01
The Lakes ZulalVilla project · 306 registered unitsRecorded complete1002006-01-012009-11-012026-11-01

The Springs

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
Emirates Living - Springs 1Villa project · 242 registered unitsRecorded complete1002005-02-012005-02-012026-11-01
Emirates Living - Springs 10Villa project · 322 registered unitsRecorded complete1002005-01-012005-01-012026-11-01
Emirates Living - Springs 11Villa project · 484 registered unitsRecorded complete1002004-10-012008-05-292026-11-01
Emirates Living - Springs 12Villa project · 308 registered unitsRecorded complete1002005-01-012005-01-012026-11-01
Emirates Living - Springs 14Villa project · 408 registered unitsRecorded complete1002004-10-012004-10-012026-11-01
Emirates Living - Springs 15Villa project · 478 registered unitsRecorded complete1002004-10-012004-10-012026-11-01
Emirates Living - Springs 2Villa project · 484 registered unitsRecorded complete1002005-02-012005-02-012026-11-01
Emirates Living - Springs 3Villa project · 450 registered unitsRecorded complete1002004-01-012004-01-012026-11-01
Emirates Living - Springs 4Villa project · 320 registered unitsRecorded complete1002004-01-012004-04-012026-11-01
Emirates Living - Springs 5Villa project · 272 registered unitsRecorded complete1002004-12-012004-12-012026-11-01
Emirates Living - Springs 6Villa project · 197 registered unitsRecorded complete1002004-12-012004-12-012026-11-01
Emirates Living - Springs 7Villa project · 268 registered unitsRecorded complete1002004-09-012004-09-012026-11-01
Emirates Living - Springs 8Villa project · 304 registered unitsRecorded complete1002005-01-012005-01-012026-11-01
Emirates Living - Springs 9Villa project · 318 registered unitsRecorded complete1002005-01-012005-01-012026-11-01

The Sustainable City

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
The Sustainable CityVilla project · 498 registered unitsRecorded complete1002017-04-272015-12-012026-11-01

The Valley

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
The Valley - AlanaVilla project · 322 registered unitsNot recorded complete81.56Not suppliedNot recorded2026-11-01
The Valley - AlvaVilla project · 196 registered unitsNot recorded complete02030-03-31Not recorded2026-11-01
The Valley - AvenaVilla project · 322 registered unitsNot recorded complete24.472028-06-30Not recorded2026-11-01
The Valley - Avena 2Villa project · 332 registered unitsNot recorded complete42.892028-07-31Not recorded2026-11-01
The Valley - EdenVilla project · 362 registered unitsRecorded complete1002023-06-032023-06-032026-11-01
The Valley - EleaVilla project · 128 registered unitsNot recorded complete22.022028-06-30Not recorded2026-11-01
The Valley - EloraVilla project · 430 registered unitsRecorded complete1002026-09-302026-03-132026-11-01
The Valley - ElvaVilla project · 244 registered unitsNot recorded complete25.862028-10-31Not recorded2026-11-01
The Valley - Farm GroveVilla project · 482 registered unitsNot recorded complete102028-12-31Not recorded2026-11-01
The Valley - Farm Grove 2Villa project · 290 registered unitsNot recorded complete9.772028-10-31Not recorded2026-11-01
The Valley - KaiaVilla project · 156 registered unitsNot recorded complete19.132028-07-31Not recorded2026-11-01
The Valley - LilliaVilla project · 406 registered unitsRecorded complete100Not supplied2026-07-202026-11-01
The Valley-NaraVilla project · 372 registered unitsRecorded complete1002024-12-302024-12-302026-11-01
The Valley - NimaVilla project · 520 registered unitsNot recorded complete80.02Not suppliedNot recorded2026-11-01
The Valley - OraniaVilla project · 308 registered unitsRecorded complete1002025-12-312025-12-312026-11-01
The Valley - RivanaVilla project · 486 registered unitsNot recorded complete95.242027-03-31Not recorded2026-11-01
The Valley - RiveraVilla project · 378 registered unitsNot recorded complete3.942028-11-30Not recorded2026-11-01
The Valley - TaliaVilla project · 330 registered unitsRecorded complete1002025-03-312025-03-312026-11-01
The Valley - VeloraVilla project · 488 registered unitsNot recorded complete50.072028-08-31Not recorded2026-11-01
The Valley - Velora 2Villa project · 312 registered unitsNot recorded complete40.282028-07-31Not recorded2026-11-01
The Valley - VeneraVilla project · 696 registered unitsNot recorded complete51.72028-09-30Not recorded2026-11-01
The Valley - VinderaVilla project · 745 registered unitsNot recorded complete1.982028-12-31Not recorded2026-11-01

The World Islands

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
Amali IslandVilla project · 24 registered unitsNot recorded complete16.372027-03-31Not recorded2026-11-01
Marbella Resort Hotel, a Vignette Collection world Islands DubaiApartment project · 153 registered unitsNot recorded complete46.85Not suppliedNot recorded2026-11-01
The Heart of Europe 1Villa project · 32 registered unitsNot recorded complete86.182022-09-30Not recorded2026-11-01
The Heart of Europe 2Apartment project · 1,383 registered unitsNot recorded complete93.422025-04-30Not recorded2026-11-01
Zaya Zuha IslandVilla project · 27 registered unitsNot recorded complete81.12025-06-30Not recorded2026-11-01

Tilal Al Ghaf

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
AmaraVilla project · 116 registered unitsNot recorded complete70.8Not suppliedNot recorded2026-11-01
AuraVilla project · 808 registered unitsRecorded complete1002024-08-312025-10-132026-11-01
ElanVilla project · 916 registered unitsRecorded complete1002023-11-032023-11-032026-11-01
Plagette 32Villa project · 32 registered unitsNot recorded complete60.57Not suppliedNot recorded2026-11-01

Town Square

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
AltonApartment project · 145 registered unitsNot recorded complete5.152028-05-31Not recorded2026-11-01
Ascot ResidencesApartment project · 140 registered unitsRecorded complete1002024-11-012024-11-012026-11-01
AugustaApartment project · 151 registered unitsNot recorded complete5.332028-01-14Not recorded2026-11-01

Dubai project register

Record type
Project register directory
Data date
Evidence base
2692 published projects; register dates 2026-11-01
Sources
Dubai Land Department project and title registers
Canonical record
/off-plan/projects/page/26
Method
Definitions and calculations

Cite as: Dubai Wealth Index. Dubai project register. Register dates 2026-11-01. https://dubaiwealthindex.com/off-plan/projects/page/26