Arjan upcoming supply
Every pending apartment project in Arjan, by when it is due, set against the homes let there today. Prices and yields in Arjan · Off-plan launches
- Data to
- Pending projects
- 21
- Pending units
- 8,265
Arjan: 4,562 apartments planned for 2026–2028, 33% of the homes let there today
Counted against today, 2026-10-18. Register to 2026-07-06; leases to 2026-10-12.
- Planned 2026–28
- 4,562
- 8,265 pending in all
- Homes let today
- 13,783
- Ejari tenancies in force
- Planned ÷ homes let
- 33%
- 0.3× a year of leasing
- Due in 12 months
- 1,861
- 2,065 already past their date
When it is due
Every pending apartment, by its registered completion quarter.
Handover calendar
Apartment units, by planned completion quarter
- Late: 2.1k2,065
- Q4 ’26: 1.0k1,023
- Q1 ’27: 616616
- Q2 ’27: 00
- Q3 ’27: 222222
- Q4 ’27: 323323
- Q1 ’28: 1.2k1,177
- Q2 ’28: 00
- Q3 ’28: 00
- Q4 ’28: 833833
- 2029 +: 570570
- No date: 1.4k1,436
Which homes, against which lets
Planned for 2026–2028 by bedroom type, against the homes of that type let today.
Planned apartments
Units due 2026–2028, by bedroom type
- Studio1,970
- 1 bed1,879
- 2 bed554
- 3 bed159
Planned as a share of homes let today
Planned units ÷ registered tenancies in force
- Studio42%
- 1 bed32%
- 2 bed19%
- 3 bed64%
How the pressure has moved
Each point is one monthly report: the same measure, recomputed for that month's end.
Planned supply as a share of homes let
Planned units for the next three calendar years ÷ tenancies in force, %
Project calendar
21 pending projects, 8,265 units. Progress is the register's reported share built.
Planned date passed2,065 units · 7 projects
- Vincitore Volare2025-06-0139632%
- Elano by ORO242025-10-0133922%
- Gardens 22025-12-3020840%
- Samana Skyros2026-04-3043671%
- Samana Mykonos Signature2026-04-3027686%
- Rose Gardens 32026-05-024276%
- Binghatti Hillcrest2026-10-0136860%
2026 Q41,023 units · 3 projects
- One Beverly2026-12-0138173%
- Trinity By Karma2026-12-0130931%
- Empire Estates2026-12-3133360%
2027 Q1616 units · 1 project
- Ashley Hills2027-03-3161620%
2027 Q3222 units · 1 project
- Floarea Grande2027-08-142222%
2027 Q4323 units · 2 projects
- Bond Enclave2027-11-301583%
- Parkside Boulevard2027-12-2716514%
2028 Q11,177 units · 1 project
- The central downtown2028-03-311,1774%
2028 Q4833 units · 2 projects
- Marquis One2028-12-314890%
- Samana Imperial Garden2028-12-313440%
2029 Q1570 units · 1 project
- Butterfly2029-01-315700%
No planned date1,436 units · 3 projects
- Kyoto by ORO24No planned date70817%
- Vincitore Dolce VitaNo planned date4797%
- Marquis InsigniaNo planned date2495%
Method and limits
Planned supply is every apartment unit in a project the Land Department register lists as neither complete nor cancelled, placed by its registered completion date and counted against today. Homes let today are the registered Ejari tenancies in force on the data date. A planned date is the developer's, not a delivery forecast; completions slip, and some homes are owner-occupied or let short-term.
Why tenancies and not the register: the unit register only reaches back to recently registered projects, so it misses most of the homes standing today. Ejari records every registered lease with its start and end. Full methodology
Arjan upcoming apartment supply
- Record type
- Planned supply against tenancies
- Data date
- Evidence base
- 8,265 pending apartment units in 21 projects; 13,783 tenancies in force
- Sources
- Dubai Land Department project and unit registers; Ejari tenancies
- Canonical record
- /supply/apartments/dubai/arjan
Cite as: Dubai Wealth Index. “Arjan upcoming apartment supply.” Arjan, Dubai. Data to 2026-10-12. https://dubaiwealthindex.com/supply/apartments/dubai/arjan