Off-plan projects in Dubai: progress register · page 17

1,286 projects not recorded complete · 1,380 recorded complete · 26 recorded cancelled.

Search and filter projects →

Check projects that have not yet been recorded complete, including those with no ready-sale evidence. Construction progress and dates come from the Dubai Land Department register; a planned date is not a forecast and 100% progress alone does not establish handover.

Of the 1,286 projects not recorded complete, 1,286 have a reported progress percentage and 1,138 have a planned completion date. “Not supplied” means the register did not provide that field. Records dated 2026-11-01.

This directory includes every published named apartment or villa project with at least ten registered units. Smaller and unnamed register entries are outside this publication cohort. Open a project for its evidence, progress history where available and source dates.

Looking for one project, or for “not complete, 50–90% built, planned date passed”? Search and filter the register.

Jumeirah Garden City

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
Trillium HeightsApartment project · 56 registered unitsNot recorded complete61.572025-12-31Not recorded2026-11-01
VibeApartment project · 207 registered unitsNot recorded complete1.492028-08-31Not recorded2026-11-01
Villea WestApartment project · 229 registered unitsNot recorded complete4.062027-11-01Not recorded2026-11-01
WAHA LIVING by AL YAKKAApartment project · 71 registered unitsRecorded complete1002025-09-302026-04-072026-11-01
West 5 ResidencesApartment project · 129 registered unitsNot recorded complete8.242027-04-14Not recorded2026-11-01
Whitestone ResidenceApartment project · 47 registered unitsNot recorded complete3.042026-10-31Not recorded2026-11-01

Jumeirah Golf Estates

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
AlandalusApartment project · 215 registered unitsRecorded complete1002019-02-282018-06-152026-11-01
ALandalus Building DApartment project · 136 registered unitsRecorded complete1002020-04-042020-04-042026-11-01
Alandalus Building EApartment project · 89 registered unitsRecorded complete1002020-08-312020-08-312026-11-01
Alandalus Building GApartment project · 29 registered unitsRecorded complete1002021-04-282021-04-282026-11-01
AL Andalus Phase 2Apartment project · 120 registered unitsRecorded complete1002019-12-312019-12-312026-11-01
Jasmine LaneVilla project · 138 registered unitsRecorded cancelled1002025-01-102025-01-102026-11-01
Jumeirah LuxuryVilla project · 165 registered unitsRecorded complete1002021-06-302021-06-302026-11-01
Signature MansionsVilla project · 18 registered unitsNot recorded complete86.942026-05-25Not recorded2026-11-01
Terra Golf CollectionVilla project · 77 registered unitsNot recorded complete20.052027-12-31Not recorded2026-11-01

Jumeirah Islands

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
Eltiera HeightsApartment project · 355 registered unitsNot recorded complete3.012028-12-31Not recorded2026-11-01
Eltiera ViewsApartment project · 1,180 registered unitsNot recorded complete02029-12-31Not recorded2026-11-01
Jumeirah Heights ClustersApartment project · 246 registered unitsRecorded complete1002012-02-012012-02-012026-11-01
Jumeirah Heights FrondsApartment project · 1,372 registered unitsNot recorded complete32.12013-01-01Not recorded2026-11-01
Jumeirah Islands MansionsVilla project · 767 registered unitsRecorded complete1002012-01-112012-01-112026-11-01
Serenia District - EastApartment project · 809 registered unitsNot recorded complete1.122030-06-30Not recorded2026-11-01
Serenia District - WestApartment project · 419 registered unitsNot recorded complete2.822028-12-31Not recorded2026-11-01

Jumeirah Lake Towers

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
Al Seef IIApartment project · 210 registered unitsRecorded complete1002008-11-062008-11-062026-11-01
Alshera TowerApartment project · 241 registered unitsRecorded complete1002008-01-302008-01-302026-11-01
Armada TowersApartment project · 789 registered unitsRecorded complete1002010-01-102010-01-102026-11-01
Banyan Tree Residences Hillside DubaiApartment project · 235 registered unitsRecorded complete1002020-05-152020-05-152026-11-01
Bonnington Tower Hotel & Residence DubaiApartment project · 271 registered unitsRecorded complete1002009-05-112009-05-112026-11-01
Concorde TowerApartment project · 472 registered unitsRecorded complete1002008-04-192008-04-192026-11-01
Diamondz By DanubeApartment project · 1,214 registered unitsNot recorded complete18.5Not suppliedNot recorded2026-11-01
Dubai Arch TowerApartment project · 384 registered unitsRecorded complete1002009-05-242009-05-242026-11-01
Dubai StarApartment project · 230 registered unitsRecorded complete1002018-11-012015-12-312026-11-01
Global Lake ViewApartment project · 331 registered unitsRecorded complete1002010-01-272010-01-272026-11-01
Gold Crest ExecutiveApartment project · 324 registered unitsRecorded complete1002009-09-022009-09-022026-11-01
Gold Crest VIEWS2Apartment project · 487 registered unitsRecorded complete1002010-02-162010-02-162026-11-01
Hilton Residences Dubai Jumeirah Lakes TowersApartment project · 398 registered unitsNot recorded complete62.97Not suppliedNot recorded2026-11-01
Indigo TowerApartment project · 272 registered unitsRecorded complete1002008-02-172008-02-172026-11-01
J&g PlexsApartment project · 583 registered unitsRecorded complete1002006-04-162006-04-162026-11-01
Jumeirah Business CENTRE2Villa project · 0 registered unitsRecorded complete1002010-01-312010-01-312026-11-01
Laguna TowerApartment project · 307 registered unitsRecorded complete1002012-08-302012-08-302026-11-01
Lake City TowerApartment project · 422 registered unitsRecorded complete1002008-09-232008-09-232026-11-01
Lake Shore TowerApartment project · 399 registered unitsRecorded complete1002009-08-112009-08-112026-11-01
Lakeside ResidenceApartment project · 358 registered unitsRecorded complete1002012-12-172012-12-172026-11-01
Lake TerraceApartment project · 544 registered unitsRecorded complete1002008-05-132008-05-132026-11-01
Lake ViewApartment project · 509 registered unitsRecorded complete1002009-02-042009-02-042026-11-01
Madina TowerApartment project · 200 registered unitsRecorded complete1002007-11-142007-11-142026-11-01
Mbl ResidenceApartment project · 471 registered unitsRecorded complete1002021-03-222021-03-222026-11-01
MBL RoyalApartment project · 330 registered unitsRecorded complete1002025-03-312025-03-312026-11-01
MBL SignatureApartment project · 459 registered unitsNot recorded complete60.12027-03-31Not recorded2026-11-01
Me Do ReApartment project · 383 registered unitsRecorded complete1002024-01-242024-01-242026-11-01
Me Do Re 2Apartment project · 396 registered unitsNot recorded complete97.782025-12-31Not recorded2026-11-01
Mercer HouseApartment project · 600 registered unitsNot recorded complete18.112027-07-31Not recorded2026-11-01
New Dubai GATE1Apartment project · 591 registered unitsRecorded complete1002010-03-142010-03-142026-11-01
New Dubai GATE2Apartment project · 446 registered unitsRecorded complete1002018-10-082018-10-082026-11-01
Orra The EmbankmentApartment project · 303 registered unitsRecorded complete1002023-08-012026-01-292026-11-01
PalladiumApartment project · 212 registered unitsRecorded complete1002007-11-122007-11-122026-11-01
Saba 4Apartment project · 535 registered unitsNot recorded complete30.352027-06-01Not recorded2026-11-01
Saba Tower 2Apartment project · 366 registered unitsRecorded complete1002008-03-062008-03-062026-11-01
Saba Tower 3Apartment project · 347 registered unitsRecorded complete1002008-01-262008-01-262026-11-01
Seven City JLTApartment project · 2,617 registered unitsNot recorded complete28.372025-11-24Not recorded2026-11-01
Signature Lifestyle ResidencesApartment project · 187 registered unitsNot recorded complete8.062028-12-31Not recorded2026-11-01
Sobha CentralApartment project · 2,022 registered unitsNot recorded complete2.382031-12-31Not recorded2026-11-01
Sobha Central Phase IApartment project · 2,383 registered unitsNot recorded complete7.082030-06-30Not recorded2026-11-01
Sobha Central Phase IIApartment project · 2,142 registered unitsNot recorded complete6.422030-06-30Not recorded2026-11-01
The ResidencesApartment project · 81 registered unitsRecorded complete1002019-07-312019-07-312026-11-01
The Wind Tower IApartment project · 486 registered unitsNot recorded complete74.582023-06-05Not recorded2026-11-01
The Wind Tower IIApartment project · 198 registered unitsNot recorded complete84.542023-06-05Not recorded2026-11-01
Uh East by EllingtonApartment project · 377 registered unitsNot recorded complete62.752026-03-30Not recorded2026-11-01
Uh West by EllingtonApartment project · 377 registered unitsNot recorded complete83.722026-03-03Not recorded2026-11-01
V3Apartment project · 328 registered unitsRecorded complete1002009-11-102009-11-102026-11-01
Verde by SobhaApartment project · 606 registered unitsNot recorded complete852027-06-30Not recorded2026-11-01
Viewz 1 By DanubeApartment project · 560 registered unitsNot recorded complete66.472026-06-30Not recorded2026-11-01
Viewz 2 By DanubeApartment project · 560 registered unitsNot recorded complete65.012026-06-30Not recorded2026-11-01

Jumeirah Park

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
Jumeirah ParkVilla project · 1,787 registered unitsRecorded complete1002014-02-262014-01-262026-11-01
Jumeirah Park 7aVilla project · 218 registered unitsRecorded complete1002016-04-302015-07-312026-11-01
Jumeirah Park 7b&cVilla project · 176 registered unitsRecorded complete1002016-02-282016-02-282026-11-01
Jumeirah Park Package 1aVilla project · 247 registered unitsRecorded complete1002015-09-282015-09-282026-11-01
Jumeirah Park - Package 5aVilla project · 134 registered unitsRecorded complete1002015-02-012015-06-172026-11-01
Royal ParkVilla project · 40 registered unitsRecorded complete1002020-09-142020-09-142026-11-01

Jumeirah Village Circle

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
105 Residences by KamdarApartment project · 105 registered unitsNot recorded complete12.452027-02-28Not recorded2026-11-01
10 OXFORD by IMANApartment project · 430 registered unitsNot recorded complete91.25Not suppliedNot recorded2026-11-01
1wood ResidenceApartment project · 219 registered unitsNot recorded complete93.67Not suppliedNot recorded2026-11-01
1wood Residence 2Apartment project · 191 registered unitsNot recorded complete02027-10-20Not recorded2026-11-01
311 Boulevard by Bam EskanApartment project · 396 registered unitsNot recorded complete102027-10-01Not recorded2026-11-01
368 Park LnApartment project · 211 registered unitsNot recorded complete02028-08-31Not recorded2026-11-01
7 Park Central by MeteoraApartment project · 118 registered unitsNot recorded complete90.182025-04-30Not recorded2026-11-01
7 West VillasVilla project · 14 registered unitsRecorded complete1002015-12-082016-03-012026-11-01
99 Park PlaceApartment project · 99 registered unitsNot recorded complete902025-12-31Not recorded2026-11-01
Ab CavalierApartment project · 162 registered unitsRecorded complete100Not supplied2026-04-232026-11-01
Aces ChateauApartment project · 51 registered unitsRecorded complete1002019-06-182019-06-182026-11-01
AlcoveApartment project · 80 registered unitsRecorded complete1002018-05-062018-05-062026-11-01
Alef Noon ResidenceApartment project · 111 registered unitsRecorded complete1002025-03-312025-03-312026-11-01
Alfal ResidencesApartment project · 283 registered unitsNot recorded complete24.912027-02-28Not recorded2026-11-01
Allura Residences by Citi DevelopersApartment project · 263 registered unitsNot recorded complete7.792027-07-27Not recorded2026-11-01
Almaan 101Apartment project · 101 registered unitsNot recorded complete50.862026-04-13Not recorded2026-11-01
Al Serh Residences 11 by Asak Real Estate DevelopmentApartment project · 102 registered unitsRecorded complete1002025-02-282026-06-042026-11-01
Alta View SkyhomesApartment project · 499 registered unitsNot recorded complete5.822029-06-30Not recorded2026-11-01
AriaApartment project · 125 registered unitsRecorded complete1002021-03-102021-03-102026-11-01
Artistic VillasVilla project · 12 registered unitsRecorded complete1002017-03-062015-09-182026-11-01
Ashton Park ResidencesApartment project · 99 registered unitsRecorded complete100Not supplied2026-02-232026-11-01
Ashton Park Residences The SecondApartment project · 194 registered unitsNot recorded complete70.052025-12-31Not recorded2026-11-01

Dubai project register

Record type
Project register directory
Data date
Evidence base
2692 published projects; register dates 2026-11-01
Sources
Dubai Land Department project and title registers
Canonical record
/off-plan/projects/page/17
Method
Definitions and calculations

Cite as: Dubai Wealth Index. Dubai project register. Register dates 2026-11-01. https://dubaiwealthindex.com/off-plan/projects/page/17