Dubai South
2 of Dubai South’s 9 dated live projects are past the completion date it registered itself: 22%, against 13% across the 28 Dubai developers with ten or more registered projects. Its most-traded tower, South Square - S1, registered 156 sales in the last 12 months at a median AED 1.63M (AED 1,527/sqft).
Live projects past their registered date
22%2 of 9
28 developers with ten or more projects: 13%
- Registered projects
- 26
- Completed
- 13
- Live, no registered date
- 4
Does Dubai South deliver on time?More of its live projects are past their own dates than Dubai’s share; its most-traded tower sells at a typical AED 1.63M (AED 1,527/sqft)
- Are live projects on time?2 of 9 dated live projects are past the date Dubai South registered; 4 more carry no date22%Context
- How does it rank?17th of the 22 developers ranked on delivery, fewest overdue first; Dubai’s share past date is 13%17thContext
- How late, typically?Only 4 completions carry a date distinct from the plan: 9 of 13 were stamped with itNo record
- Do its towers trade?South Square - S1 trades at AED 1,527/sqft on 156 sales, off-plan and ready, in 12 months; 17 of its towers have a sale recordAED 1.63MContext
Ranked on the share of live projects past their own registered date · fewest first · register Jul 2026
Live projects, most advanced firstSouth Bay 1 is 91% built and 16 months past its date
Built % and dates from the DLD register, Jul 2026 · months past date at that register date · a live project past its date is overdue, not late: it has not been delivered, and this site does not forecast when it will be
Delivered projects, most recent first13 completed, 9 dated to the registered day
Show the 13 delivered projectsHide the delivered projects
Slippage is months from the registered date to the recorded one; negative is early. The register dates 9 of these 13 completions to the registered day exactly — it writes the completion date onto the planned one — so those are marked “stamped” and left out of the median rather than counted as on time. 4 measurable completions are too few to publish a median (the floor is 5).
Dubai South towers on the marketIts towers trade between AED 830 and 1,527 per sqft
Registered sales, ready and off-plan, in the 12 months to · attribution follows the project each tower was registered under · the 8 most traded of 17
Every project the Dubai Land Department registers to Dubai South, matched by the developer licence number on each registration — a medium-confidence identity.
Common questions
- Are Dubai South's off-plan projects on time?
- 2 of Dubai South's 9 dated live projects are past the completion date the developer registered itself (22%), against 13% across the 28 Dubai developers with ten or more registered projects. Being past the date is a fact about today, not a forecast of when a project will finish. Dubai Land Department project register to 2026-07-06.
- How does Dubai South rank against other Dubai developers on delivery?
- Dubai South ranks 17th of the 22 developers ranked on delivery, fewest live projects past their registered date first. Only developers with at least 5 live projects are ranked. Dubai Land Department project register to 2026-07-06.
- How late are Dubai South's completed projects, typically?
- Not enough to say: only 4 of its 13 completed projects carry a completion date distinct from the registered one, so no median slippage is published. Dubai Land Department project register to 2026-07-06.
- How many projects has Dubai South registered in Dubai?
- 26 registered projects: 13 live, 13 completed. Projects are matched to Dubai South by the developer licence number on each registration. Dubai Land Department project register to 2026-07-06.
- What do Dubai South's towers sell for?
- Its most-traded tower, South Square - S1, sold at a median AED 1,527/sqft across 156 registered sales, off-plan and ready, in the last 12 months. These are prices paid, not asking prices.
For agents
Send Dubai South’s delivery record to a client
Dubai South, delivery record
- Record type
- Developer-level off-plan register record
- Data date
- Evidence base
- 26 registered projects, 13 live of which 2 past their registered date, 4 completions with a measurable slippage of 13 completed; DLD project register as of 2026-07-06; identity medium-confidence over 1 licensed company
- Sources
- Dubai Land Department project register
- Canonical record
- /developers/dubai-south
Cite as: Dubai Wealth Index. “Dubai South, delivery record.” Register to 2026-07-06, data to 2026-10-12. https://dubaiwealthindex.com/developers/dubai-south