Danube Properties, delivery record

Registered projects
38
DLD register, Jul 2026
Live past their registered date
46%
6 of 13 live projects with dates · 8 without dates
Median slippage
-4months
6 measurable completions
Completed
17
11 dated to the registered day

Every project the Dubai Land Department registers to Danube Properties, matched by the developer licence number on each registration — a high-confidence identity. A live project past the completion date the developer itself registered is counted as overdue, not as late: it has not been delivered yet, and this site does not forecast when it will be.

The register dates 11 of this developer’s 17 completed projects to the registered day exactly — it writes the completion date onto the planned one — so those show no slippage in either direction and are excluded from the figure above rather than counted as delivered on time.

Live projects

21 registered and not yet recorded complete, most advanced first.

Delivered projects

17 recorded complete, most recent first. Slippage is months from the registered date to the recorded one; negative is early.

ProjectLocalityRegisteredCompletedSlippage, months
Opalz By DanubeDubai Science ParkApr 2025Apr 2025on time
GEMZ by DanubeAl FurjanMar 2025Mar 2025on time
PEARLZ by DanubeAl FurjanJan 2025Jan 2025on time
Jewelz ResidenceArjanOct 2023Oct 2023on time
Olivz ResidenceAl WarsanJul 2023Jul 2023on time
Wavez ResidenceLiwanSept 2022Sept 2022on time
ELZ ResidenceArjanMay 2022May 2022on time
Lawnz Residence by DanubeInternational CityFeb 2022Feb 2022on time
Bayz TowerBusiness BayMay 2021May 2021on time
Glamz ResidenceAl FurjanOct 2020Oct 2020on time
Resortz ResidenceArjanFeb 2020Sept 2019-5
Miraclz TowerArjanApr 2021Jul 2019-21
STARZ TOWER by DANUBEAl FurjanFeb 2019Feb 2019on time
Glitz Residence 3Dubai Studio CityFeb 2018Nov 2017-3
Glitz Residence 1Dubai Studio CityJul 2017Jul 2017on time
Glitz Residence 2Dubai Studio CityJul 2017Jul 2017on time
DreamzAl FurjanMar 2018Mar 2016-24

Danube Properties, delivery record

Record type
Developer-level off-plan register record
Data date
Evidence base
38 registered projects, 21 live of which 6 past their registered date, 6 completions with a measurable slippage of 17 completed; DLD project register as of 2026-07-06; identity high-confidence over 1 licensed company
Sources
Dubai Land Department project register
Canonical record
/developers/danube-properties
Method
Definitions and calculations

Cite as: Dubai Wealth Index. “Danube Properties, delivery record.” Register to 2026-07-06, data to 2026-09-11. https://dubaiwealthindex.com/developers/danube-properties