Off-plan projects in Dubai: progress register · page 23

1,286 projects not recorded complete · 1,380 recorded complete · 26 recorded cancelled.

Search and filter projects →

Check projects that have not yet been recorded complete, including those with no ready-sale evidence. Construction progress and dates come from the Dubai Land Department register; a planned date is not a forecast and 100% progress alone does not establish handover.

Of the 1,286 projects not recorded complete, 1,286 have a reported progress percentage and 1,138 have a planned completion date. “Not supplied” means the register did not provide that field. Records dated 2026-11-01.

This directory includes every published named apartment or villa project with at least ten registered units. Smaller and unnamed register entries are outside this publication cohort. Open a project for its evidence, progress history where available and source dates.

Looking for one project, or for “not complete, 50–90% built, planned date passed”? Search and filter the register.

Majan

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
Aras HeightsApartment project · 73 registered unitsRecorded complete1002023-12-312026-03-122026-11-01
ARAS ResidenceApartment project · 96 registered unitsRecorded complete1002022-06-222022-06-222026-11-01
BARARIGATE by ADEApartment project · 274 registered unitsNot recorded complete1.672028-12-31Not recorded2026-11-01
Barari PalaceApartment project · 221 registered unitsNot recorded complete0.042028-12-30Not recorded2026-11-01
Barari Parks By BahatApartment project · 46 registered unitsNot recorded complete0.92028-03-31Not recorded2026-11-01
Barari Parkview by Al MawaredApartment project · 195 registered unitsNot recorded complete44.72027-12-20Not recorded2026-11-01
Barari ViewsApartment project · 26 registered unitsRecorded complete1002024-03-232025-11-072026-11-01
Binghatti Skyflame 1Apartment project · 1,378 registered unitsNot recorded complete02027-12-31Not recorded2026-11-01
Binghatti Skyflame 2Apartment project · 782 registered unitsNot recorded complete02027-12-31Not recorded2026-11-01
Binghatti TitaniaApartment project · 789 registered unitsNot recorded complete02027-02-28Not recorded2026-11-01
Binghatti VintageApartment project · 1,572 registered unitsNot recorded complete02027-03-31Not recorded2026-11-01
Blossom 40Apartment project · 66 registered unitsNot recorded complete0.042028-03-31Not recorded2026-11-01
Bottega Nove by LalavApartment project · 54 registered unitsNot recorded complete30.042027-07-30Not recorded2026-11-01
Celia HeightsApartment project · 188 registered unitsRecorded complete100Not supplied2026-07-162026-11-01
DEANSGATE by ADEApartment project · 82 registered unitsRecorded complete100Not supplied2026-02-042026-11-01
Divine Al BarariApartment project · 291 registered unitsNot recorded complete20.322028-03-31Not recorded2026-11-01
Estrella by NexusApartment project · 60 registered unitsNot recorded complete45.52026-05-31Not recorded2026-11-01
Forest City TowerApartment project · 228 registered unitsNot recorded complete70.082027-04-09Not recorded2026-11-01
Forum 2Apartment project · 77 registered unitsNot recorded complete7.032027-12-15Not recorded2026-11-01
Forum ResidencesApartment project · 46 registered unitsRecorded complete1002023-03-312023-03-312026-11-01
Jade TowerApartment project · 434 registered unitsNot recorded complete112027-03-31Not recorded2026-11-01
Lazord by LapisApartment project · 304 registered unitsNot recorded complete27.642026-12-31Not recorded2026-11-01
Madison ResidenceApartment project · 117 registered unitsRecorded complete1002013-09-252013-09-252026-11-01
Paradise View 1Apartment project · 203 registered unitsRecorded complete1002018-11-222018-11-222026-11-01
Rabdan GatesApartment project · 437 registered unitsNot recorded complete5.182028-06-30Not recorded2026-11-01
Rijas SuitesApartment project · 153 registered unitsNot recorded complete3.332028-12-31Not recorded2026-11-01
Samana Barari HeightsApartment project · 694 registered unitsNot recorded complete4.042028-10-31Not recorded2026-11-01
Samana Barari LagoonsApartment project · 526 registered unitsNot recorded complete16.522028-03-31Not recorded2026-11-01
Samana Barari ViewsApartment project · 669 registered unitsNot recorded complete26.812027-03-31Not recorded2026-11-01
Samana Barari Views 2Apartment project · 669 registered unitsNot recorded complete19.65Not suppliedNot recorded2026-11-01
SamayaApartment project · 212 registered unitsRecorded complete1002019-07-312019-07-312026-11-01
Sherena ResidenceApartment project · 300 registered unitsRecorded complete1002017-03-152017-03-152026-11-01
Sherena Residence 2Apartment project · 120 registered unitsNot recorded complete82.032022-08-31Not recorded2026-11-01
Symphony by ChaimaaApartment project · 64 registered unitsNot recorded complete02027-08-31Not recorded2026-11-01
The 50Apartment project · 60 registered unitsRecorded complete1002020-07-312020-07-312026-11-01
The HavenApartment project · 322 registered unitsRecorded complete1002025-07-122025-07-122026-11-01
The Haven IIApartment project · 221 registered unitsNot recorded complete56.292026-12-31Not recorded2026-11-01
The Haven IIIApartment project · 81 registered unitsNot recorded complete6.172027-12-31Not recorded2026-11-01
Tulip Oasis 10Apartment project · 127 registered unitsRecorded complete1002026-06-302026-06-292026-11-01
Tulip Oasis 11Apartment project · 99 registered unitsNot recorded complete93.012026-06-30Not recorded2026-11-01
Vincitore Wellness EstateApartment project · 1,475 registered unitsNot recorded complete02030-02-15Not recorded2026-11-01
Wadi 645Apartment project · 70 registered unitsNot recorded complete55.15Not suppliedNot recorded2026-11-01
Zubaida ResidencyApartment project · 62 registered unitsRecorded complete100Not supplied2023-01-182026-11-01

Maritime City

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
Aria By BeyondApartment project · 191 registered unitsNot recorded complete84.862026-01-31Not recorded2026-11-01
Breez by DanubeApartment project · 1,188 registered unitsNot recorded complete0.142029-06-30Not recorded2026-11-01
Chelsea Residences 2 by DAMACApartment project · 958 registered unitsNot recorded complete5.442029-12-31Not recorded2026-11-01
Chelsea Residences by DAMACApartment project · 703 registered unitsNot recorded complete5.192029-12-31Not recorded2026-11-01
Coral ReefApartment project · 279 registered unitsNot recorded complete32.87Not suppliedNot recorded2026-11-01
Franck Muller YachtingApartment project · 574 registered unitsNot recorded complete02028-07-29Not recorded2026-11-01
Harbour LightsApartment project · 294 registered unitsNot recorded complete64.312027-05-21Not recorded2026-11-01
IL VentoApartment project · 330 registered unitsNot recorded complete1.152029-09-30Not recorded2026-11-01
Kanyon By BeyondApartment project · 411 registered unitsNot recorded complete02028-09-30Not recorded2026-11-01
LIV MaritimeApartment project · 255 registered unitsNot recorded complete28.122028-12-30Not recorded2026-11-01
Mar CasaApartment project · 580 registered unitsNot recorded complete56.452026-10-31Not recorded2026-11-01
Nautica OneApartment project · 328 registered unitsNot recorded complete85.19Not suppliedNot recorded2026-11-01
Nautica TwoApartment project · 328 registered unitsNot recorded complete85.45Not suppliedNot recorded2026-11-01
Oceanz 1 By DanubeApartment project · 530 registered unitsNot recorded complete50.04Not suppliedNot recorded2026-11-01
Oceanz 2 By DanubeApartment project · 775 registered unitsNot recorded complete42.03Not suppliedNot recorded2026-11-01
Oceanz 3 By DanubeApartment project · 386 registered unitsNot recorded complete20.64Not suppliedNot recorded2026-11-01
OriseApartment project · 530 registered unitsNot recorded complete17.642027-11-30Not recorded2026-11-01
Prestige One ResidencesApartment project · 214 registered unitsNot recorded complete0.112029-12-31Not recorded2026-11-01
Riva ResidenceApartment project · 152 registered unitsRecorded complete1002025-09-252025-12-262026-11-01
SariaApartment project · 368 registered unitsNot recorded complete30.992027-10-01Not recorded2026-11-01
SensiaApartment project · 275 registered unitsNot recorded complete17.542029-03-30Not recorded2026-11-01
Soulever' By BeyondApartment project · 513 registered unitsNot recorded complete02028-12-30Not recorded2026-11-01
TaleaApartment project · 354 registered unitsNot recorded complete02028-06-30Not recorded2026-11-01
The Anwa by OmniyatApartment project · 229 registered unitsRecorded complete1002021-12-132021-11-152026-11-01
The MuralApartment project · 265 registered unitsNot recorded complete16.642028-07-10Not recorded2026-11-01
The PierApartment project · 278 registered unitsNot recorded complete48.442026-12-31Not recorded2026-11-01

Meydan

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
ARTHOUSE RESIDENCES TOWER A by AVIAANApartment project · 46 registered unitsNot recorded complete02027-11-30Not recorded2026-11-01
Azizi GardensApartment project · 77 registered unitsRecorded complete1002023-12-112023-12-112026-11-01
Azizi GreenfieldApartment project · 89 registered unitsRecorded complete1002024-03-082024-03-082026-11-01
Azizi Park AvenueApartment project · 108 registered unitsRecorded complete1002024-01-182024-01-182026-11-01
Bright CornerApartment project · 40 registered unitsRecorded complete1002019-09-292019-09-292026-11-01
Emerge ResidencesApartment project · 78 registered unitsNot recorded complete21.132027-11-01Not recorded2026-11-01
Flamingo Lux ResidenceApartment project · 50 registered unitsRecorded complete1002025-05-052026-06-092026-11-01
Grand ViewsVilla project · 305 registered unitsRecorded complete1002020-02-242019-11-152026-11-01
Maybach SixApartment project · 1,844 registered unitsNot recorded complete02027-08-31Not recorded2026-11-01
Maybach Ultimate LuxuryApartment project · 1,204 registered unitsNot recorded complete02027-08-31Not recorded2026-11-01
Prime ViewsApartment project · 151 registered unitsRecorded complete1002020-04-302021-03-022026-11-01
Project MaybachApartment project · 816 registered unitsNot recorded complete02027-06-30Not recorded2026-11-01
Rabdan AvenueApartment project · 147 registered unitsNot recorded complete02029-03-01Not recorded2026-11-01
Rabdan SquareApartment project · 33 registered unitsNot recorded complete1.242028-03-01Not recorded2026-11-01
Royal ManorApartment project · 35 registered unitsRecorded cancelled77.812018-12-152022-11-162026-11-01
Saddlewood ParkApartment project · 61 registered unitsNot recorded complete12.452027-09-30Not recorded2026-11-01
Sukoon by NuriApartment project · 38 registered unitsNot recorded complete46.772026-12-31Not recorded2026-11-01
The 100Apartment project · 90 registered unitsRecorded complete1002025-03-192025-03-192026-11-01
The Derby Residence 2&3Apartment project · 60 registered unitsRecorded cancelled1002018-07-012015-04-282026-11-01
The GalleriesApartment project · 45 registered unitsRecorded complete1002019-02-042019-02-042026-11-01
The Polo ResidenceApartment project · 871 registered unitsRecorded complete1002017-05-172017-06-052026-11-01
Tonino Lamborghini ResidencesApartment project · 541 registered unitsRecorded cancelled602026-12-312022-08-242026-11-01
Vedaire ResidencesApartment project · 43 registered unitsNot recorded complete02028-03-31Not recorded2026-11-01
Vision IconicApartment project · 1,426 registered unitsNot recorded complete02028-12-15Not recorded2026-11-01
Woodland CrestApartment project · 50 registered unitsNot recorded complete1.42027-06-30Not recorded2026-11-01

Meydan One

Register status, reported progress and dates; apartment and villa titles remain distinct.

ProjectStatusBuilt, %Planned completionRecorded completion / cancellationRegister date
Azizi Riviera 1Apartment project · 378 registered unitsRecorded complete1002024-07-252024-07-252026-11-01
Azizi Riviera 10Apartment project · 129 registered unitsRecorded complete1002022-09-302022-08-232026-11-01
Azizi Riviera 11Apartment project · 131 registered unitsRecorded complete1002022-09-302022-09-132026-11-01
Azizi Riviera 12Apartment project · 131 registered unitsRecorded complete1002022-09-302022-09-302026-11-01
Azizi Riviera 13Apartment project · 220 registered unitsRecorded complete1002022-04-302022-11-102026-11-01
Azizi Riviera 14Apartment project · 215 registered unitsRecorded complete1002022-09-302023-05-252026-11-01

Dubai project register

Record type
Project register directory
Data date
Evidence base
2692 published projects; register dates 2026-11-01
Sources
Dubai Land Department project and title registers
Canonical record
/off-plan/projects/page/23
Method
Definitions and calculations

Cite as: Dubai Wealth Index. Dubai project register. Register dates 2026-11-01. https://dubaiwealthindex.com/off-plan/projects/page/23